Sunday, March 3, 2013

Insullation in...getting warmer...

From one day to the next the basement and main floor are now fully insullated. They work fast!


We also met with Brad from Leggo Kitchens who we have hired to do our kitchen and bathroom vanities. Of all of the kitchen suppliers that we went to for quotes Brad was the absolute easiest to deal with, not to mention he gave us the most reasonable price. So far we are very pleased with his work. I can't wait to see the final product. We picked out colours today for the kitchen cabinets and vanities. We went with a medium tone with a darker glaze on it, its called Mocha Glaze. At first I was leaning towards the darker browns but I worried about whether 5-6 years down the road would it still be something I loved? I guess we played it safe but I do like it and I think it will look nice. I'm a bit worried about what it will look like with our dining room set (which I am not crazy about). The dining room set has a reddish undertone to it and it is pretty dark. But I didn't want to design the kitchen around the dining room set, which can be easily replaced. The kitchen is pretty perminent. The picture below is the colour for all of the cabinets including bathroom vanities. The colour swatch on top is the pick for the bathroom vanities. We still have to go pick out the granite for the kitchen...but I have seen one that I like called Sienna Bordeaux.
 
Above is the granit I had picked out before. Brad is going to get us a piece of maple stained and glazed the way we want it so that we can take it with us when we go to pick out the granite. I also need to go get a sample piece of the ceramic tile and hardwood floors we picked out.
We had already gone out and had a look at flooring and picked these out, but this was before we picked out cabinets so this might change.Its a maple 8" planks, hand scraped and distressed hardwood, and the tiels are 18x18 ceramics.
The next couple of weeks are going to get busy!

Wednesday, February 27, 2013

Electrical Passed!

I couldn't be prouder of my hubby! We had our electrical inspection today and we passed with flying colours. They didn't even need to go down to the basement and check out the electrical panel. They saw that he had done such a nice job on the main level he didn't feel like he needed to go downstairs.
Tomorrow the dry wall guys start first thing in the morning to start installing insullation and drywall.

Oscar is watching the kids out the window...Guard Dog!

Ready for insullation and drywall tomorrow

Tuesday, February 26, 2013

Finally settled on Kitchen design

After a couple of months of going to different cabinet makers for pricing and designs we have finally settled on a design by Leggo Kitchens from Woodstock. He was very easy to deal with, very accommodating and gave us a great price.





 This is the design for the kitchen. I liked the staggered look of the cabinets and the wine rack. Over the stove we've decided to do a stainless steel hood fan like the one above. The island we have changed the design of again so that it is all one level rather than having the one side drop down to table height. I like the idea of there being more counter space to work with, it will also be a good surface for putting food and stuff on for get togethers. And if people come over and I'm in the kitchen when they sit at the island we'll be eye to eye.

Now we just have to go finalize the colour of the cabinets and counter tops, hardware etc. But at least we are settled on our "guy". We went through a few to find him but he is great.

Brick pick...

I've picked colours/finishes for the exterior of the house...

Morning smoke is the colour of the brick, weatherwood for the roof and that small sample is the colour for the garage doors and exterior trim and fascia on the house. The front door is a mahogany stained door.

This is the outdoor pendant light for the front entrance, in front of the mahogany door.

Now we just need some nice weather so that we can get the exterior work started!

Sunday, February 24, 2013

Wires, wires and more wires!

No new pics to post but we have some more progress. Hubby has been working his butt off every day after work. As of today we are officially ready for insulation and drywall. He has wired the whole house for hydro, lights, cable, computers, and speaker systems. We had the alarm system installed this weekend too. We have contracted someone to come and do the insulation and drywall next week after our inspection for the electrical is done on Wednesday.
Wish us luck!


Tuesday, February 5, 2013

Slow and Steady...Oh and SOLD!!!

My posts are falling behind, but only because this dumb blogger site won't always let me post pics! So our house sold. Our closing date is March 28th. Our house won't be ready by then I'm sure so we'll have to go stay with my in laws for at least a month. We are hoping for end of April for our place to be ready, but it is hard to predict at this point.

Anyway, the roof is on and shingled. We have windows, which look so good. We got windows with pewter grills on the inside, and the grills are just along the outsides of the window not through the window like most windows have. The pewter is really subtle and looks nice.
My hubby has literally been working his butt off  - literally - he has lost quite a bit of weight the bastard! He works from 6-2 everyday and then heads over to the house and works there until supper time. He'll come home and eat and then go back and work till about 930-10 almost every night. He has had a hand in almost every step in the progress so far. The furnace and water heater are in. The duct work is done. We have our inspection by Union Gas tomorrow to make sure everything is in good order. He has been working on the electrical and has a lot done so far. I have to give credit where credit is due. He will really be able to say that he helped build his family home.

The plumbing is getting done the a contractor friend out of Mount Pleasant. This will at least be getting done through the day and then hubby can go in and continue to work on the electrical. We were hoping to be able to start drywalling soon.

We are almost settled on the kitchen design and I think this is what we are going with more or less.
Maple Cabinet - Autumn BrownThis is the colour I'm thinking for the cabinetsThis is kind of what I'm thinking for the counter top. I found one I like but I couldn't find the exact picture of it online. But I think it was similar to this.
 
Getting busy picking out things like lighting now too. And I've started packing  - I hate packing.
 
Anyway, no new pics of the house yet but nothing really worth taking pics of right now. But I will continue to keep you posted on our progress.

 

Sunday, January 13, 2013

We have walls!

I can't believe its been almost a month since I last posted!

There has been quite a bit going on at the house. My hubby has been hard at work on the septic and well system. We have framers on site now, lots going on!

Just before Christmas we contracted a framer out of Kitchener. On Dec 27, 28th they came out and brought a big container that had to be brought in on a flat bed truck with all of their tools and equipment. And Jan 2nd they got started. When I went to the house on Jan 5th, this is what I found:
 

 
I was pleasantly surprised! I couldn't believe how much was actually done already. BUT  - when I stepped into the house I had a bit of an anxiety attack. It just looks so small on the inside. I started to panic! Is everything going to fit in here, it looks like everything is going to be so tight! I went as far as to go back the next day with the drawings and a tape measure just to try to map out where everything was going to be. I know I am over reacting. The main area of the new house is the size of our main level minus the front dining/living room area. I think its just different for me. I'm used to having our front entrance about 20 feet or so from the kitchen/family room. Now with the new house you walk in and there is small entrance before you enter the main area of the house. Its just different, not what I'm used to right now.

As of this week, this is what we've got:
 
 
CRAZY PROGRESS!!! The roof will be ready for shingles by this coming Thursday or Friday. So my job this week is to pick out a brick colour and shingles.
 
My hubby and good friend of ours D were busy today with doing some electrical work and more work on the sump pump. With all of this rain we had about 3 inches of water in the basement. They are getting ready to start running the electrical and putting in junction boxes and switches etc etc...
 
It's coming along and I am starting to get excited although there is still soooo much work to do.